Construction of the Central Ring Road of Moscow region (with subsequent maintenance on a fee basis)

Total length of all planned sections of the Central Ring Road
521 km
Estimated speed of traffic
150 km/h
Number of lanes at the first stage
4-8

Following the results of the implementation of the Long-Term Programme of Activity of the State Company (2010 – 2019) it is planned that 3 highway start-up complexes of 321 km will be put into operation.



Action taken

km

Period of implementation

Construction of start-up complex No.3 on the section from the intersection with the high speed M-11 Moscow-St. Petersburg highway to the intersection with the M-7 Volga federal highway.
1052013-2017
Construction of start-up complex No.4 on the section from the intersection with the M-7 Volga federal highway to the intersection with the M-4 Don federal highway.
972015-2019
Construction of start-up complex No.1 on the section from the M-4 Don federal highway to the intersection with the M-1 Belarus highway.
1192014-2021