14 July 2020

The works on construction of motorway junction through the body of M-5 "Ural" Highway are in progress on the Central Ring Road-4 around the clock

Construction of artificial structures at the Fourth Launch Complex of the Central Ring Road (CRR-4), including the motorway junctions through the body of the blocked section M-5 "Ural" is in progress around the clock.

The main route of CRR-4 will take place under M-5, upon completion of the construction of this interchange, motorists will be able to both drive off and enter the ring road from Moscow and Bronnitsy. After opening the traffic along the main route of the ring road, they will be able to reduce travel time in order to get to M-7 "Volga" Highway and M-4 "Don" Highway without driving through the Moscow Ring Road (MRR).

Currently,  active works on the installation of bored piles are in progress in the left direction. In the right direction, the motorway junction stands have high degree of readiness.

From June 1 up to November 15, 2020, on M-5 "Ural" Highway, the traffic pattern from A-107 Moscow Small Ring (MSR) to the entry to Novoryazanskoye Highway (a turn towards Starnikovo village) was changed. The construction workers make every effort to restore traffic on the blocked section ahead of schedule.

The length of CRR-4 is 96.846 kilometers. It passes through four districts (Noginsk, Pavlovsky Posad, Voskresensk and Ramenskoye) and through two urban districts (Elektrostal and Domodedovo) of the Moscow Region. 71 engineering structures are being erected on it, including six transport interchanges.