CONSTRUCTION OF THE HIGH SPEED M-11 MOSCOW – ST. PETERSBURG HIGHWAY (KM 258 – KM 334, VYSHNY VOLOCHEK BYPASS)
Location |
Tver Region (Vyshny Volochek bypass) |
Section length |
72 km |
Traffic load (predicted) |
12 000 – 15 000 cars/day |
Road category |
1А |
Estimated speed of traffic |
150 km/h |
Number of Lanes |
4 |
Total project cost, billion roubles (in 2011 prices) |
46.5 |
State funding |
90% |
Private funding |
10% |
Contract type |
Long-term investment agreement with contractor investment obligations |
Contract term |
23 years |
Term of tende |
tender announced in 2011 |
Period of construction |
2012 - 2014 |