Total length of all planned sections of the Central Ring Road | 521 km |
Estimated speed of traffic | 150 km/h |
Number of lanes at the first stage | 4-8
|
Following the results of the implementation of the Long-Term Programme of Activity of the State Company (2010 – 2019) it is planned that 3 highway start-up complexes of 321 km will be put into operation.
Action taken |
km |
Period of implementation |
Construction of start-up complex No.3 on the section from the intersection with the high speed M-11 Moscow-St. Petersburg highway to the intersection with the M-7 Volga federal highway. | 105 | 2013-2017
|
Construction of start-up complex No.4 on the section from the intersection with the M-7 Volga federal highway to the intersection with the M-4 Don federal highway. | 97 | 2015-2019 |
Construction of start-up complex No.1 on the section from the M-4 Don federal highway to the intersection with the M-1 Belarus highway. | 119 | 2014-2021 |